OFI FILTER HOUSE — MAJOR DIESEL FILTRATION FACILITY

Garden Island, WA

EIG delivered the mechanical construction along with the electrical design, and commissioning assurance of a major diesel filtration facility on Garden Island. This facility is capable of filtering 1200L/minute of Diesel fuel and was comprised of two high volume pre-filtration vessels, six high volume coalesces and filtration vessels.

Despite the perceived difficulties that the client foresaw EIG would encounter in delivering the complex and critically important project, EIG completed the project ahead of an already advanced schedule.

Client: Australian Defence Force / Duratec Limited

RAAF PEARCE ELECTRICAL WORKS (CEPS)

Bullsbrook & Gingin, WA

EIG completed the upgrade of the central emergency power station. This included the installation of a new back-up power station, with HV generators, fuel system, HV panels and control system. All systems were fully integrated into the active site.

EIG were engaged as integration specialists and were able to reduce client costs, allowing budget reallocation to complete further upgrades to systems in other areas.The additional funds allowed for HV cable upgrades as RAAF Pearce and an upgrade to the load bank and a new smart battery backup for the power station at RAAF Gingin.

EIG completed the high-risk work and minimised the impact on site operations, all whilst completing a planned stage cutover into an active site.

Client: Australian Defence Force / Duratec Limited

HAZARDOUS AREAS COMPLIANCE

HMAS Stirling, Garden Island WA & RAAF Pearce, Bullsbrook WA

EIG were engaged to inspect, design and rectify electrical installations across multiple Australian Defence Force sites. This included detailed grade inspections of existing explosion protected equipment within hazardous areas, compilation of inspection reports and surveys noting any non-conformances.

EIG replaced multiple systems including hazardous compliant control systems, fire systems, distribution boards, lighting, power and earthing systems. Hazardous Area Verification Dossiers were then created for all hazardous areas.

Our specialist team were able to quickly adapt to all the individual requirements they were confronted with when working in such niche and high-risk environments.

Working closely together with the client, EIG Australia helped in achieving substantial cost-savings by adjusting both the types of hazardous substances being utilised and how they are stored. These changes resulted in greatly reduced outlay costs, future maintenance expenses, and most importantly the reduced size of the overall hazardous area footprint on the defence bases.

Client: Australian Defence Force / Duratec Limited

CAMPBELL BARRACKS LIGHT VEHICLE WORKSHOP

Swanbourne, WA

EIG designed and constructed a complete lubrication facility for the light vehicle workshop at Campbell Barracks. This consisted of the entire design and construction of the mechanical and electrical systems, including code 61 high pressure stainless steel piping for six lubricants and coolants. The hose reel racks were in groups of six on custom built racks in four locations.

EIG designed the custom lubrication dispensing and storage system to the client’s specifications, and installed the system within a sea container module, allowing the client to re-locate the facility to a new location if necessary.

Client: Australian Defence Force / Duratec Limited

SMALL BOAT HARBOUR – MECHANICAL AND ELECTRICAL OVERHAUL OF PUMPING/FILTRATION UNIT

Garden Island, WA

EIG completed the electrical and mechanical design and construction of both the mechanical and electrical overhaul of the Moresby Wharf refuelling and filtration facility.

The project consisted of the demolition of the existing facility, and the enhanced design and construction of a new diesel refuelling facility and two large coalesces.

EIG utilised contemporary mechanical equipment and electrical systems. This provided improved safety, advanced instrumentation, and smoother operational procedures.

Client: Australian Defence Force / Duratec Limited

PEARCE AIRCRAFT CONTROL TOWER – LIGHTNING PROTECTION & AIRCRAFT OBSTACLE LIGHTING

RAAF Pearce, Bullsbrook WA

EIG were engaged to install various systems within the Aircraft Control Tower and the Communications buildings. Works included the coring and certification of penetrations, supply and installation of cable containment, distribution boards, UPS systems, functional earthing systems, new lightning protection systems and the supply of new aircraft obstacle lighting.

EIG were agile with all aspects of the installation. Tasked with short time frames, EIG completed the works fluently to ensure that there was no impact to the crucial operations of the client.

Client: Australian Defence Force / Duratec Limited

AVCAT TANK BUND REMEDIATION

Garden Island, WA

EIG performed all electrical, communications, process control and commissioning activities required to assist the client in the renewal and upgrade of the concrete tank bunding on Garden Island.

Client: Australian Defence Force / Duratec Limited

RAAF GINGIN TRANSMITTER BUILDING

RAAF Gingin, Gingin WA

EIG were engaged for various works within the Transmitter building at RAAF Gingin. Works included the supply and installation of distribution boards, functional earthing systems, UPS system, cabling upgrades and the coring and certification of penetrations.

Client: Australian Defence Force / Duratec Limited

RCD COMPLIANCE

Various Sites, WA

EIG completed site wide RCD compliance across nine defence bases in WA. These works included the remediation of all existing switchboards and adhering to compliance with Australian Standards.

The project was delivered on schedule and within budget.

Client: Australian Defence Force / Duratec Limited

LANCELIN FIRING POINT ALPHA

Lancelin, WA

EIG completed the design, supply and installation of a contained power generator system to supply multiple off-grid buildings. Works included the generator supply and installation, generator fuel system, generator cooling system, distribution boards, fire system and general electrical works.

Tasked with sophisticated works in a remote location, our specialist team, through vigorous planning, achieved the project on-time and to budget.

Client: Duratec Limited

HMAS STIRLING HARDSTAND

Garden Island, WA

EIG together with Australian Maintenance Services (AMEIG) were engaged to install a new maintenance hardstand at Garden Island. This included an ablution block, area lighting, power distribution and SCADA integration.

EIG delivered the project within budget and on schedule. The hardstand provided facilities for the Australian Defence Force to manage subcontractor operations from a central location. Smart metering also allowed for monitoring of subcontractor power usage.

Client: Australian Defence Force / Duratec Limited

ELECTRICAL SEWER UPGRADES

RAAF Pearce, Bullsbrook WA

EIG were engaged to replace multiple sewer control panels, pumps and level switches throughout RAAF Pearce, Bullsbrook. Works included the upgrade of existing single-phase supplies to three phase supplies. Temporary control systems were installed to ensure the continued functionality of the sewers were maintained during the upgrade works taking place.

Client: Australian Defence Force / Duratec Limited